Road Doctor Engineering Limited, Adafat Integrated Services Limited and Goldenjist Engineering Limited were the companies used to ‘execute’ a road project in Kwali Council Area of the Federal Capital Territory that was never completed for 10 years, Beloved John reports.
When the first construction company visited Bako village in 2015, the villagers were delighted as it was a pleasant surprise. They anticipated the end of the project, which they assumed to be a neatly tarred road and a good drainage system.
The road at the time was filled with potholes and some parts destroyed by erosion. During rainy seasons, it was murky, almost unusable for pedestrians, and for car owners.
The villagers’ hopes withered away with time as they watched the construction stall intermittently, sometimes for a prolonged period until it deteriorated to a more damaged state.
According to residents who spoke to SOLACEBASE, the construction workers cleared the road, poured laterite on the surface, which covered potholes, dug out a shallow waterway by the sides of the road and they left.
While the residents anticipated their return the following week, months grew into years without showing up again. The sand on the road surface was later washed away by rainfall, creating new potholes which made the road more difficult for use. Multiple sources told this newspaper that the road project was abandoned for four years, as no further work was carried out on the road until 2019.
Delay
The 14 kilometre road stretches from Bako into Dabi and Bobota village, connecting three neighbouring communities. It is called the Bako-Bobota road and the project was awarded by the Kwali area council along with the Federal Capital Territory Administration. Although SolaceBase could not find total releases for the road project, the chairman of the Federal Capital Territory Administration (FCTA) disclosed that the road construction was part of some projects commissioned with N306 million in 2014.
When N156 million was again allocated to the internal road project to the FCTA in 2019, an audit report obtained by our reporter shows that N55 million was paid as upfront to Goldenjist Engineering Limited. The audit report revealed that the project had been abandoned and the payment didn’t match the work done. It also observed that proper procedures weren’t followed when awarding the contract.
Residents told SolaceBase that in 2019, the construction company returned, graded the road, and built drainages in both the Dabi and Bako axis. According to the community village head, Danladi Bako, the road was abandoned multiple times due to disagreements on finances as the contractor complained about non-payment of funds by the Kwali Local Government Council.
“There was a financial issue between the constructor and the Kwali council so the constructor stopped working. First, the work was suspended between 2015 and 2019. Then in 2019, the company returned to work for a period and stopped.”
Re-awarded
In 2021, the project was revoked from Goldenjist Engineering Limited and re-awarded to two companies — Road Doctor Engineering Limited and Adafat Integrated Service Limited by the Kwali Council Chairman. Since then, there has not been any significant improvement on the road.
“When the men came to work in 2021, they poured laterite on the road and added stones, as though they were about to finally complete the project, but they left again,” said Abiola Saki, a resident of Bako community. He recalls the time clearly as it was exactly three months after she moved into the neighbourhood, and harboured a little resentment for the road for its poor state. From her shop where she sold food items, she watched as the men worked on the road.